The DuPont schedule, explained
The DuPont schedule is a 28-day, four-crew rotation of 12-hour shifts that is commonly credited to the chemical company DuPont, which is said to have developed it for its plants in the 1950s. Each crew works four nights, takes three days off, works three days, takes one day off, works three nights, takes three days off, works four days and then takes a full week off. The seven-day break is the whole point.
The 28 days in plain order
- 4 night shifts
- 3 days off
- 3 day shifts
- 1 day off
- 3 night shifts
- 3 days off
- 4 day shifts
- 7 days off
| M 1 | T 2 | W 3 | T 4 | F 5 | S 6 | S 7 | M 8 | T 9 | W 10 | T 11 | F 12 | S 13 | S 14 | M 15 | T 16 | W 17 | T 18 | F 19 | S 20 | S 21 | M 22 | T 23 | W 24 | T 25 | F 26 | S 27 | S 28 | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Crew A | N | N | N | N | D | D | D | N | N | N | D | D | D | D | ||||||||||||||
| Crew B | N | N | N | N | D | D | D | N | N | N | D | D | D | D | ||||||||||||||
| Crew C | D | D | D | D | N | N | N | N | D | D | D | N | N | N | ||||||||||||||
| Crew D | D | D | D | N | N | N | D | D | D | D | N | N | N | N |
Four crews start the cycle a week apart, so every shift is covered and every crew gets its week off in turn. The cycle is exactly four weeks, which is why the weekday of day 1 stays important: the same blocks land on the same weekdays every four weeks.
A DuPont year in numbers
- 182.5 shifts and 2,190 hours, the same as other 12-hour rotations.
- 52 work stretches, far fewer than Pitman, because the work comes in longer blocks.
- One seven-day break every 28 days, about 13 a year. A week away costs 0 to 4 shifts of leave if you pick the right window, and 14 days costs as few as 4.
- About 91 night shifts a year, the same as Panama.
The hard part: one day off between days and nights
After the three-day block there is only one day off before the next three nights. That is the single toughest turn in the cycle, and it is the main reason people either love DuPont (the week off) or leave it (the quick flip). The other switch, nights to days, has three days off, which is easier. If you work DuPont, plan sleep carefully around the one-day gap.
Weekends and the start date
Because the cycle is exactly four weeks, the blocks line up with the same weekdays every month. In the best alignment you get half of all weekends off, in the worst none. The table below shows every start weekday for your crew. It also shows overtime on a strict 40-hour week, which for DuPont is the most uneven of the 12-hour patterns because the week with four 12-hour days in a row can reach 60 or 72 hours.
| If day 1 of the cycle is a | Weeks of (hours) | Full weekends off per year | Most weekends worked in a row | Overtime hours per year over 40 a week |
|---|---|---|---|---|
| Monday | 0, 48, 72 | 26 | 2 | 626 |
| Tuesday | 12, 48, 60 | 26 | 2 | 469 |
| Wednesday | 24, 48 | 13 | 3 | 313 |
| Thursday | 36, 48 | 13 | 3 | 209 |
| Friday | 36, 48 | 26 | 2 | 209 |
| Saturday | 24, 48 | 26 | 2 | 313 |
| Sunday | 12, 48, 60 | 0 | 4 | 469 |
On a strict 40-hour week the DuPont gives between 209 and 626 overtime hours a year depending on where the workweek starts, and many sites define the workweek to land on the best alignment. Ask your payroll office.
Who it suits
- People who use time off in big pieces. Travel, school terms, a second job or a long project fit the 7-day break.
- Sites that want fewer shift handovers. Long stretches keep the same crew on the same job for four days in a row.
Who finds it hard
- Anyone who needs weekly routines. The days off move around.
- People who struggle with the quick flip from the three days block to the three nights block.
- Night-sensitive sleepers. Every crew works nights twice in each cycle, so there is no stable sleep pattern for long.
Numbers on this page are calculated from the standard DuPont cycle and rounded. Your employer's posted roster is the official schedule. Last reviewed November 2026.