Round-the-clock work has one hard constraint: a week has 168 hours, and one person can only work a fraction of them. A rotating schedule is the repeating plan that hands those 168 hours to a small number of teams so that every hour has someone on duty and every person still gets time off. Understanding a handful of ideas makes any roster easier to read.
The arithmetic of coverage
Divide the 168 hours in a week by the hours one person works in an average week and you get the number of crews a site needs. If people work 42 hours a week, 168 ÷ 42 is exactly four crews. If they work 56 hours, 168 ÷ 56 is exactly three crews. If they work 40 hours a week, 168 ÷ 40 is 4.2, which is why 8-hour rosters with a 40-hour week need extra relief staff and why plants that use four crews on 8-hour shifts, like the continental schedule, end up at 42 hours.
| Shift length | Average hours per week | Crews needed for 24/7 | Where you see it |
|---|---|---|---|
| 8 hours | 40 | 4.2, so 5 | Office-style rosters, some retail and 8-hour plants |
| 8 hours, 24/7 | 42 | 4.0, so 4 | Continental and other three-shift plants |
| 12 hours | 42 | 4.0, so 4 | Pitman, Panama, DuPont, 4 on 4 off |
| 24 hours | 56 | 3.0, so 3 | 24/48, 48/96 and Kelly in fire and EMS |
This is the reason 12-hour rotations average 42 hours and 24-hour rotations average 56. It is not a coincidence or a quirk of any one employer. It is the only way the numbers close.
Crews, cycles and offsets
- A crew is a team that works the same shifts together, named with a letter such as A, B, C or D.
- A cycle is the number of days before a crew's pattern repeats. The 24/48 cycle is 3 days. The DuPont cycle is 28.
- An offset is how far one crew's start is from crew A's. In the Pitman, crew B starts seven days after crew A, which is why one of them is always working.
Every crew on a pattern runs the same cycle. They just start it on different days. That is why you can read a whole site's roster from a single row of the cycle.
Fixed versus rotating
In a fixed pattern like the Pitman, each crew stays on days or on nights. Your body clock settles, but the people on nights stay on nights for good. In a rotating pattern like the Panama, DuPont or Continental, every crew moves through the day and night shifts, so nights are shared. The cost is that your body has to switch repeatedly.
Forward and backward rotation
If a crew moves from mornings to afternoons to nights, it is rotating forward. Moving the other way is backward. Many occupational health sources favor forward rotation, because delaying your sleep by a few hours is easier than advancing it. The continental schedule is a clean example of forward rotation. See the NIOSH guide to shiftwork for background.
Blocks and breaks
Two patterns with the same weekly hours can feel different because of how the time off is cut. The Pitman never gives more than three days off in a row, while the DuPont gives one full week off every 28 days. The 4 on 4 off gives four days after every block. These shapes are what you are really choosing when you pick a roster.
Why the start date matters
A cycle only has a place on the calendar once you give it a start date. If the cycle length is a multiple of seven, as in the 14-day Pitman or the 28-day DuPont, the pattern lands on the same weekdays every cycle, so the weekday of day 1 decides which weekends you get. If the cycle length is not a multiple of seven, as in the 16-day 4 on 4 off, weekends drift evenly. Our weekend study counts them for every pattern.
How to read a posted roster
- Find your crew letter and the shift type you start on.
- Find day 1 of your cycle on the calendar. It is usually the first day of a work block.
- Count forward through the cycle. Every day after that follows the pattern until the cycle starts over.
- Check the result against the next two weeks of the posted roster. If it matches, it will match for the rest of the year, unless the employer changes it.
The calendar on each pattern page does steps 2 and 3 for you. If your calendar does not match your roster, the crew or the start date is wrong, or your employer uses a variation.
Where to go next
Pick a pattern and open its calendar: Pitman, Panama, DuPont, 4 on 4 off, 24/48, 48/96, Kelly, Continental, 9/80. If your rotation is not on the list, build it in the custom schedule builder.
Quick answers
How many crews do you need to cover 24/7?
Divide 168 hours by the hours one person works in a week. At 42 hours a week you need four crews. At 56 hours a week you need three.
What is the difference between a fixed and a rotating schedule?
In a fixed pattern a crew stays on one shift type. In a rotating pattern every crew moves through days and nights.
What is a cycle?
The number of days before the pattern repeats. A 24/48 repeats every 3 days and a DuPont every 28.
Edited and reviewed by Adriano Mendes. Figures are calculated from the standard patterns on this site and rounded. This is general information, not legal, payroll or medical advice. Last updated November 2026.